Azizi Developments has announced that 41% of the construction work on Azizi Vista, located in Dubai Studio City, one of the most exclusive residential areas in Dubai, has been completed.
The project, which consists of studios, one-bedroom and two-bedroom apartments, is scheduled for completion in the first quarter of 2025. With approximately 23% of the overall finishes completed, Azizi Vista is making significant progress.
The structural work is 100% complete, while the blockworks have reached 96%, the interior cladding is 74%, in addition to 39% of the heating, air conditioning and ventilation works, and 36% of the electrical, mechanical and plumbing works, while the total workforce on site has been increased to 447 workers.
Azizi Vista is progressing with exceptional speed and craftsmanship thanks to the company’s stringent quality control protocols, strong partnerships and advanced construction techniques, said Farhad Azizi, CEO of Azizi Developments.